Australian offshore decommissioning / Public records

Australian offshore records

Edition 01: ten official records, reviewed 18 September 2026, expanding each quarter. Each entry separates scope, assessment outcome and reported commencement, with links to the original source.

An independent, source-cited register of Australian offshore decommissioning activity, compiled from public regulator publications.

For operators, analysts, researchers and media.

Each entry reports the regulator’s published status, with its source link and checked date. Statuses are reported, never interpreted.

Corrections, 18 September 2026: BMG Closure Project Phase 2 status updated to “Under assessment (with NOPSEMA)”; Echo Yodel Subsea Decommissioning rechecked and retained as “Under assessment (with titleholder)”; Petrel-3 and Petrel-4 notified stop added (7 September 2026).

Reading this reference

These are industry records, not Endura project credits. The selection is not a complete national inventory or a live progress tracker. Follow each original source for its current status.

Return to the technical library →
Edition 01 / 18 Sep 2026

Explore by region.

Selected records, not a national census. Checked dates describe source review, not site inspection.

Method & corrections ↓Edition briefing →
10 selected records
EP 8306

Gippsland Basin Decommissioning - Campaign #1 Execution Environment Plan

AcceptedGippsland

The accepted plan covers a heavy-lift removal campaign and transfer of removed structures for onward transport. Its published schedule anticipates activity from Q3 2026 to Q1 2028.

What this record coversUp to 13 platform topsides; Upper jackets of up to 10 steel-piled facilities; Two monotowers, removed to seabed
  1. Submitted
  2. Environment plan accepted
Notified commencement
Pending titleholder notification
Completion
Not established by this record
Source location
Commonwealth waters, 21 to 77 km off eastern Victoria.
Basin named in source
Gippsland Basin

Start notification remains pending. The scope describes selected structures, not complete removal of every facility component; the forecast is not evidence of execution.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

EP 8655

Montara 1,2,3 Wellhead Removal

AcceptedAshmore Cartier

The plan provides several cutting options to recover the Montara-1, -2 and -3 wellheads. It allows an approximately 14-day campaign including vessel mobilisation and demobilisation.

What this record coversThree exploration/appraisal wellheads; ROV surveys and site preparation; Cutting, recovery and onshore handling
  1. Submitted
  2. Environment plan accepted
Notified commencement
Pending titleholder notification
Completion
Not established by this record
Source location
Montara Field, production licence AC/L7; approximately 80 m water depth.
Basin named in source
Not stated in this record

The wells' earlier plugging and abandonment does not establish wellhead removal. Removal timing is explicitly unknown and vessel-dependent; no start is notified.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

EP 8584

Julimar-Brunello Plug and Abandonment

AcceptedNorth West

The accepted plan covers MODU-based work on three exploration wells and a contingent intervention at a fourth well. The register records a titleholder-notified start on 8 May 2026.

What this record coversPermanent abandonment of three subsea wells; Wellhead cutting and possible recovery; Contingent drilling-mud remediation at Balnaves Deep-1
  1. Submitted
  2. Environment plan accepted
  3. Titleholder-notified commencement
Notified commencement
8 May 2026
Completion
Not established by this record
Source location
WA-49-L, approximately 185 km WNW of Karratha; 135 to 171 m water depth.
Basin named in source
Barrow Sub-Basin

The plan expressly excludes final field decommissioning and title surrender. Some wellhead recovery may occur under a separate EP; completion is not established.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

RMS 8935

Echo Yodel Subsea Decommissioning

Under assessment (with titleholder)North West

The revision proposes removal of the pipeline between the Goodwyn Alpha isolation structure and the Yodel wells. The published commencement window is November 2026 to January 2027, subject to approvals and delivery conditions.

What this record covers12-inch subsea pipeline; Associated pipeline equipment
  1. Submitted
Notified commencement
Unknown: not reported on this assessment page
Completion
Not established by this record
Source location
North West Shelf Province, approximately 140 km northwest of Dampier; 130 to 135 m water depth.
Basin named in source
Not stated in this record

This revision is under assessment. Historical well and umbilical work described on the page must not be presented as completion of this proposed pipeline scope.

Earlier accepted plan: EP 5222 ↗ (opens in a new tab). This is separate from the revision under assessment.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

RMS 8810

BMG Closure Project Phase 2

Under assessment (with NOPSEMA)Gippsland

The revision proposes recovery of remaining subsea infrastructure after the earlier well-abandonment phase. Approximately 75 offshore activity days are anticipated, with proposed Phase 2 completion by 31 December 2030.

What this record coversRemaining wellheads; Subsea flowlines and umbilicals; Field management and post-removal monitoring; Selected buried steel retained
  1. Submitted
Notified commencement
Unknown: not reported on this assessment page
Completion
Not established by this record
Source location
VIC/RL13, about 50 km offshore south of Cape Conran; 135 to 270 m water depth.
Basin named in source
Unknown: page identifies the Gippsland region, without separately naming a basin

The revision is under assessment. Phase 1 completion in May 2024 does not establish Phase 2 completion, and the 2030 date is a proposal.

Earlier accepted plan: EP 7074 ↗ (opens in a new tab). This is separate from the revision under assessment.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

EP 8208

North West Shelf Phase 1 Plug and Abandonment and TPA03 Well Intervention

AcceptedNorth West

The accepted campaign combines permanent abandonment of five wells with an intervention at TPA-03. The register records a titleholder-notified start on 4 February 2026.

What this record coversThree Angel wells and two Perseus-over-Goodwyn wells; Preparatory subsea work; Separate TPA-03 production-well intervention
  1. Submitted
  2. Environment plan accepted
  3. Titleholder-notified commencement
Notified commencement
4 February 2026
Completion
Not established by this record
Source location
Commonwealth waters; nearest well about 125 km north of Dampier, in 77 to 128 m water depth.
Basin named in source
Northern Carnarvon Basin

TPA-03 intervention supports potential future production and is not abandonment. The EP is not the final decommissioning or title-surrender plan; no stop is notified.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

EP 8520

Jack-Up Rig Wellwork BTA

AcceptedGippsland

The accepted plan covers jack-up-rig wellwork at Barracouta, with up to nine wells and an estimated 120-day campaign. A titleholder-notified start is recorded for 18 August 2026.

What this record coversWell abandonment and workovers; Conductor recovery; Jack-up rig positioning and support activities
  1. Submitted
  2. Environment plan accepted
  3. Titleholder-notified commencement
Notified commencement
18 August 2026
Completion
Not established by this record
Source location
Barracouta platform, VIC/L02; existing 500 m petroleum safety zone.
Basin named in source
Gippsland Basin

The description's earlier Q4 2025 forecast is not the notified start. This is a wellwork scope, not evidence that the platform has been removed.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

EP 8007

Petrel-3 and Petrel-4 Monitoring and Decommissioning

AcceptedNorthern Territory

The accepted plan covers monitoring, preparation, permanent well abandonment and a post-decommissioning seabed survey. The activity page records a titleholder-notified start on 4 September 2026 and stop on 7 September 2026.

What this record coversTwo suspended wells; Inspection and seabed surveys; Permanent abandonment and subsea-equipment recovery
  1. Submitted
  2. Environment plan accepted
  3. Titleholder-notified commencement
  4. Titleholder-notified stop
Notified commencement
4 September 2026
Notified stop
7 September 2026
Completion
Not established by this record
Source location
Petrel-3 and Petrel-4 in NT/RL1; field water depth approximately 95 m.
Basin named in source
Bonaparte Basin

Equipment retention is a contingency if reasonable recovery attempts fail. The record does not establish which components have been recovered or whether abandonment is complete.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

EP 7977

Reindeer Wellhead Platform and Gas Supply Pipeline Operations and Cessation of Production

AcceptedNorth West

The accepted plan combines operations with production-cessation and preservation activities. Preserved infrastructure may remain while future reuse or decommissioning decisions are made.

What this record coversWellhead platform and associated wells; Commonwealth section of the gas pipeline; Cleaning, flushing, preservation and monitoring
  1. Submitted
  2. Environment plan accepted
Notified commencement
Unknown: start field not displayed
Completion
Not established by this record
Source location
Reindeer field, approximately 80 km northwest of Dampier.
Basin named in source
Not stated in this record

The register classifies the lifecycle as decommissioning, but this EP does not establish full removal. Its forecast cessation date is not evidence that production has ceased. The description contains inconsistent production-licence references, so none is asserted here.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

EP 7924

Ningaloo Vision Cessation of Production and Floating Asset Removal

AcceptedNorth West

The accepted plan covers floating-asset removal and management of retained infrastructure. A titleholder-notified start is recorded for 4 August 2025.

What this record coversFPSO disconnection and departure; Risers and detachable turret mooring; Selected flushing and a 910 m damaged flowline section
  1. Submitted
  2. Environment plan accepted
  3. Titleholder-notified commencement
Notified commencement
4 August 2025
Completion
Not established by this record
Source location
North West: no more specific geographic position established by the cited HTML record.
Basin named in source
Not stated in this record

Well abandonment and most subsea-infrastructure removal require separate future EPs. Some mooring recovery is conditional; the notified start does not establish completion of these components.

Read original NOPSEMA record ↗ (opens in a new tab)

Source checked: 18 September 2026 · Link to this entry

Methodology / Edition 01

Keep the claim inside the evidence.

Selection and scope

This edition contains ten selected NOPSEMA public activity or environment-plan assessment records relevant to decommissioning. It is not a complete Australian asset inventory. Records are grouped using the source’s location categories. A basin is named only where established by the cited record.

Dates and status

Submission, assessment outcome, notified commencement and completion are separate events. An accepted environment plan does not establish completed work. A revision under assessment remains distinct from an earlier accepted plan. Proposed dates are not actual dates. “Not established” identifies a limit of this review.

Map and age information

The outline supports regional orientation only. No asset coordinates or basin polygons are asserted. An age filter is omitted because a consistent installation-date basis has not been verified. Drilling date, first production and installation age are not interchangeable.

Sources and corrections

Source checks were made on 18 September 2026. Original regulatory pages remain authoritative and may change after this date. No regulator endorsement or Endura participation is implied. The index contains original short summaries and factual metadata, with links to the sources; source PDFs are not republished.

To request a correction, send the entry title, source link and the point requiring review to jed@enduradecom.com. A correction should retain the prior edition and identify the changed field, supporting source and check date.

Since the last edition

This is the baseline edition. There is no earlier edition against which to claim quarterly movement. Future editions can compare retained records on the same basis.

Download this edition · JSON